Grid connection & powerPower that is already there

A new or larger grid connection in Germany often takes months, in congested areas years. Teams running AI servers, test benches or labs rarely fail on floor space in conventional office buildings – they fail on kilowatts.

In short

How long does a new grid connection take?

It depends on power, voltage level and grid area. Examples from 2026:

CaseDurationSource
Expansion 800 kW → 2.5 MW with a new 20 kV substation (example project)14 monthsDeutsche Data Center
Lead time for a medium-voltage transformer6–12 monthsZfK / Siemens Energy
Lead time for a large power transformer (high voltage)18–36 monthsZfK / Siemens Energy
New large consumers in the congested Mittelbaden area (Netze BW, 110 kV)not before 2032–2035ZfK
Data centres from 50 MW in the Rhine-Main areaup to 13 yearsJLL

According to the Federal Network Agency, connection requests of more than 700 GW are queued nationwide. Even smaller expansions compete with this queue – and with lead times for transformers and switchgear.

How a grid connection works

  1. Connection request to the local grid operator with the required power (kW or kVA) and simultaneity.
  2. Grid compatibility check: is the upstream grid sufficient? If not, grid expansion follows – often the longest part.
  3. Offer with construction cost contribution (BKZ) and connection costs, then the grid connection contract.
  4. From a few hundred kilowatts usually medium voltage: your own substation with transformer and switchgear to VDE-AR-N 4110 – planning, delivery, construction, acceptance.
  5. Commissioning, meter installation (from 100,000 kWh a year with interval metering) and connection use contract.

Why conventional offices fall short

The PROJEKTCAMPUS advantage

Conventional office vs. campus

FeatureConventional / open-plan officePROJEKTCAMPUS
Grid connectionone service connection per building9 independent connection points, 3 in reserve
Power for your spaceoffice load, increase only via connection request25 kW per half floor, combinable
Time to powermonths to yearsfrom move-in
Meteringapportioned via service chargesown meter per half floor
Servers and racksusually not allowedallowed in your own office
Termoften 5–10 yearsmonthly

Grid connection glossary

For facility management, IT project managers and administrators – briefly explained:

Grid connection / service connection
Link between the building and the public grid; the agreed power is set in the grid connection contract.
Connection request
Application to the grid operator for a new or larger connection – the starting point of any power increase.
Low voltage (LV)
230/400 V – connection of households and most commercial spaces, rules per VDE-AR-N 4100 (TAR low voltage).
Medium voltage (MV)
usually 10 or 20 kV – for larger consumers with their own substation, rules per VDE-AR-N 4110 (TAR medium voltage).
Customer substation
your own station with medium-voltage switchgear and transformer on site, needed from a few hundred kilowatts.
Local distribution substation
the grid operator’s transformer station stepping medium down to low voltage and supplying several buildings.
TAB
technical connection conditions of the grid operator, e.g. notification and approval duties for large consumers.
Construction cost contribution (BKZ)
one-off contribution to grid expansion per kW of connected load; at medium voltage in 2026 roughly €100–150/kW depending on the operator.
kW and kVA
kW is active power, kVA apparent power; at power factor cos φ = 1 they are equal, for power supplies and motors kVA is slightly higher.
Simultaneity factor
share of devices drawing full load at the same time – determines the connected load you need.
Continuous and peak load
GPU servers often run close to full load all the time; cooling comes on top. Plan with the sum of both.
Interval metering and standard load profile
From 100,000 kWh a year, interval metering in 15-minute steps (load curve) instead of a standard load profile.
Demand charge
grid fee on the highest 15-minute load of the year – a single peak makes the whole year more expensive.
Sub-meter (MID)
calibrated meter behind the main meter used to bill individual tenants or racks by consumption.
UPS and generator
the uninterruptible power supply bridges minutes, the standby generator (diesel) takes over after seconds.
N+1 redundancy
one component more than needed so that a single failure does not stop operation.
PUE
Power Usage Effectiveness: total power divided by IT power – the closer to 1.0, the less energy for cooling.
Flexible grid connection
connection with an agreed power limit during congestion – often faster and with a lower BKZ.

Frequently asked questions

How long does a new commercial grid connection take?

A small low-voltage connection often takes a few months. With your own medium-voltage substation, rather more than a year – an example project from 800 kW to 2.5 MW took 14 months. In congested areas, large connections are sometimes only possible in the 2030s.

From what power do you need medium voltage?

The grid operator decides. Often from a few hundred kilowatts, typically between about 300 kW and 1 MW – then a dedicated substation with transformer is required.

What does a grid connection cost?

Besides connection costs there is a construction cost contribution per kW. At medium voltage, published values in 2026 were roughly €100 to €150 per kW depending on the operator – plus substation, transformer and cables.

How much power do I get at PROJEKTCAMPUS?

25 kW per half floor (about 200 m²) with its own meter, several units can be combined. The underground garage has a dedicated 250 kW connection. In total the campus has almost 2 MW.

May I run servers and racks in the office?

Yes. Racks in your own office are allowed, as are fan and air-conditioning noise. For small teams there is the AI office with up to 2 kW in a private office, for larger loads the half floor with 25 kW.

What does the power cost?

Billed by consumption via your own meter: cheapest local tariff plus 20 % provision fee. No construction cost contribution, no transformer station of your own.