Grid connection & powerPower that is already there
A new or larger grid connection in Germany often takes months, in congested areas years. Teams running AI servers, test benches or labs rarely fail on floor space in conventional office buildings – they fail on kilowatts.
In short
- almost 2 MW connected load on the campus
- 9 independent grid connection points, each below 300 kW, 3 more in reserve
- 25 kW per half floor (about 200 m²) with its own meter
- 250 kW dedicated connection in the new underground garage – for an edge data centre or vehicles
- Power at the cheapest local tariff + 20 % provision fee, billed by consumption
How long does a new grid connection take?
It depends on power, voltage level and grid area. Examples from 2026:
| Case | Duration | Source |
|---|---|---|
| Expansion 800 kW → 2.5 MW with a new 20 kV substation (example project) | 14 months | Deutsche Data Center |
| Lead time for a medium-voltage transformer | 6–12 months | ZfK / Siemens Energy |
| Lead time for a large power transformer (high voltage) | 18–36 months | ZfK / Siemens Energy |
| New large consumers in the congested Mittelbaden area (Netze BW, 110 kV) | not before 2032–2035 | ZfK |
| Data centres from 50 MW in the Rhine-Main area | up to 13 years | JLL |
According to the Federal Network Agency, connection requests of more than 700 GW are queued nationwide. Even smaller expansions compete with this queue – and with lead times for transformers and switchgear.
How a grid connection works
- Connection request to the local grid operator with the required power (kW or kVA) and simultaneity.
- Grid compatibility check: is the upstream grid sufficient? If not, grid expansion follows – often the longest part.
- Offer with construction cost contribution (BKZ) and connection costs, then the grid connection contract.
- From a few hundred kilowatts usually medium voltage: your own substation with transformer and switchgear to VDE-AR-N 4110 – planning, delivery, construction, acceptance.
- Commissioning, meter installation (from 100,000 kWh a year with interval metering) and connection use contract.
Why conventional offices fall short
- One service connection for the whole building, designed for lighting, desks and air conditioning – not for racks drawing several kilowatts continuously.
- More power means a new connection request by the owner – with construction cost contribution, waiting time and often a separate transformer station.
- Open-plan office with one meter: power is billed through service charges, your own consumption cannot be measured properly.
- Noise and heat from servers are usually not allowed in open-plan offices, 24/7 access often impossible.
The PROJEKTCAMPUS advantage
- Distributed instead of central: 9 independent connection points across several buildings, each below 300 kW. Many grid operators only require a dedicated medium-voltage substation from a few hundred kilowatts – here the power is already available in the low-voltage grid.
- Reserve in place: 3 more connection points for growth, without starting from scratch.
- Own meter per half floor: 25 kW for power and cooling, consumption measured and billed individually. Several meters can be combined – one AI tenant already uses about 100 kW continuous load this way.
- Racks allowed in your own office, fan and air-conditioning noise included, 24/7 access.
- Underground garage with 250 kW, 3 m clear height and high floor loads – space for a small edge data centre.
- Rent by the month, fibre from four providers, right on the A8 between Stuttgart and Karlsruhe.
Conventional office vs. campus
| Feature | Conventional / open-plan office | PROJEKTCAMPUS |
|---|---|---|
| Grid connection | one service connection per building | 9 independent connection points, 3 in reserve |
| Power for your space | office load, increase only via connection request | 25 kW per half floor, combinable |
| Time to power | months to years | from move-in |
| Metering | apportioned via service charges | own meter per half floor |
| Servers and racks | usually not allowed | allowed in your own office |
| Term | often 5–10 years | monthly |
Grid connection glossary
For facility management, IT project managers and administrators – briefly explained:
- Grid connection / service connection
- Link between the building and the public grid; the agreed power is set in the grid connection contract.
- Connection request
- Application to the grid operator for a new or larger connection – the starting point of any power increase.
- Low voltage (LV)
- 230/400 V – connection of households and most commercial spaces, rules per VDE-AR-N 4100 (TAR low voltage).
- Medium voltage (MV)
- usually 10 or 20 kV – for larger consumers with their own substation, rules per VDE-AR-N 4110 (TAR medium voltage).
- Customer substation
- your own station with medium-voltage switchgear and transformer on site, needed from a few hundred kilowatts.
- Local distribution substation
- the grid operator’s transformer station stepping medium down to low voltage and supplying several buildings.
- TAB
- technical connection conditions of the grid operator, e.g. notification and approval duties for large consumers.
- Construction cost contribution (BKZ)
- one-off contribution to grid expansion per kW of connected load; at medium voltage in 2026 roughly €100–150/kW depending on the operator.
- kW and kVA
- kW is active power, kVA apparent power; at power factor cos φ = 1 they are equal, for power supplies and motors kVA is slightly higher.
- Simultaneity factor
- share of devices drawing full load at the same time – determines the connected load you need.
- Continuous and peak load
- GPU servers often run close to full load all the time; cooling comes on top. Plan with the sum of both.
- Interval metering and standard load profile
- From 100,000 kWh a year, interval metering in 15-minute steps (load curve) instead of a standard load profile.
- Demand charge
- grid fee on the highest 15-minute load of the year – a single peak makes the whole year more expensive.
- Sub-meter (MID)
- calibrated meter behind the main meter used to bill individual tenants or racks by consumption.
- UPS and generator
- the uninterruptible power supply bridges minutes, the standby generator (diesel) takes over after seconds.
- N+1 redundancy
- one component more than needed so that a single failure does not stop operation.
- PUE
- Power Usage Effectiveness: total power divided by IT power – the closer to 1.0, the less energy for cooling.
- Flexible grid connection
- connection with an agreed power limit during congestion – often faster and with a lower BKZ.
Frequently asked questions
How long does a new commercial grid connection take?
A small low-voltage connection often takes a few months. With your own medium-voltage substation, rather more than a year – an example project from 800 kW to 2.5 MW took 14 months. In congested areas, large connections are sometimes only possible in the 2030s.
From what power do you need medium voltage?
The grid operator decides. Often from a few hundred kilowatts, typically between about 300 kW and 1 MW – then a dedicated substation with transformer is required.
What does a grid connection cost?
Besides connection costs there is a construction cost contribution per kW. At medium voltage, published values in 2026 were roughly €100 to €150 per kW depending on the operator – plus substation, transformer and cables.
How much power do I get at PROJEKTCAMPUS?
25 kW per half floor (about 200 m²) with its own meter, several units can be combined. The underground garage has a dedicated 250 kW connection. In total the campus has almost 2 MW.
May I run servers and racks in the office?
Yes. Racks in your own office are allowed, as are fan and air-conditioning noise. For small teams there is the AI office with up to 2 kW in a private office, for larger loads the half floor with 25 kW.
What does the power cost?
Billed by consumption via your own meter: cheapest local tariff plus 20 % provision fee. No construction cost contribution, no transformer station of your own.
More on power and infrastructure
Sources
- Soester Anzeiger/Ippen.Media, 04.10.2026: „Bis zu 13 Jahre Wartezeit“ (JLL, EU-Kommission, AWS)
- ZfK, 27.07.2026: Netzengpass in Mittelbaden (Netze BW, E-Werk Netze)
- ZfK, 22.06.2026: Trafos als Nadelöhr beim Netzausbau (Lieferzeiten)
- aktiencheck.de, 17.11.2026: Netzanschluss-Stau, über 700 GW in der Warteschlange (nach ZfK/BNetzA)
- Deutsche Data Center: Stromversorgung im Rechenzentrum (Übergabestation, USV, NEA)
- dvlp.energy: Baukostenzuschüsse 2026 im Überblick
- Vattenfall: RLM- und SLP-Zähler
- VDE FNN: Technische Anschlussregeln (TAR) Nieder- und Mittelspannung